[REFAT] Field visit to the SONEDE water pumping station at Chott El Fejij, Gabes.

[REFAT] Field visit to the SONEDE water pumping station at Chott El Fejij, Gabes.

29 June, 2021

On June 25th 2021,  the Executive Director of MEDREC, along with the project management members of REFAT and ICAPT projects, and the Energy Management Director of SONEDE, organized a field visit to the water pumping station of SONEDE located in Chott El Fejij, Gabes. 

The purpose of the visit was to supervise the progress of the landscaping construction process preceding the installation of a 512kW photovoltaic power plant for pumping drinking water, in the framework of REFAT project.

The team was welcomed on site by SATER SOLAR SA, the head of the Tunisian-Italian consortium which started the landscaping process of the plant on April 1st 2021.

The field tour included:

  • A visit to the technical/control building, inside which will be installed the electronic devices needed for the photovoltaic plant ;
  • An observation of the cooling process of the geothermal water pumped to the station;
  • A Filming of testimony and guided tour videos for the project partners and beneficiaries’.

Related News
8 June, 2021
En partenariat avec le Ministère de l’Agriculture, de la Pêche et des Ressources Hydrauliques, le Centre Méditerranéen des Énergies Renouvelables (MED.
4 June, 2021
En partenariat avec le Ministère de l’Agriculture, de la Pêche et des Ressources Hydrauliques, le Centre Méditerranéen des Énergies Renouvelables (MED.
3 June, 2021
Mode de financement : Ce projet est financé conjointement par le Ministère Italien de la Transition Écologique et le Ministère Tunisien.
1 June, 2021
The Interreg Med Renewable Energy Community selected a project proposal developed by MEDREC and DG/ACTA (Direction Generable de l’Aménagement et la Co.
18 May, 2021
This issue includes the results related to the new synergies created with other projects and initiatives, and the actions implemented in the.
4 May, 2021
In the framework of REFAT project, the National Water Distribution Utility – SONEDE started the installation of a 512kW photovoltaic power plant, for.